Salar Futuro at a glance: project summary
Salar Futuro is a $3B lithium capital project (15% market cap, of which SQM should
contribute with half of it) by Novandino Litio SpA (SQM-Codelco JV) in the Salar de
Atacama, Chile. Salar Futuro is a relevant modification to the existing operation that
supports lithium production until 2060 thought higher recoveries (DLE technology) while
modernizing infrastructure and reducing environmental constraints (eg, water usage).
The project includes restructuring the processing model through the integration of
Direct Lithium Extraction (DLE1) with other technologies (nanofiltration, mechanical
evaporation, and reverse osmosis) in a hybrid system - combining existing solar
evaporation ponds with DLE Adsorption (AD) flowsheet, similar to what Eramet
Centenario-(Ratones, Argentina), Livent/Arcadium (Fénix, Argentina), and SunResin
(multiple Chinese and Argentine deployments) have implemented.
The construction period spans 7 years (2H29-2H36) but the 2-yr DLE plant construction
is expected to be concluded in 2034. First production could commence in 2031 (brine
extraction), but enriched-DLE lithium production could commence by 2035 (Exhibit 4).
Operationally, brine extraction will be capped at maximum of 822 L/s (consistent with
prior regulatory commitments), but the project allows for higher recovery efficiency
(DLE technology delivers c. >80% lithium recovery vs 40-50% for traditional pond
evaporation) — which reduces brine intensity per tonne of LCE produced. While the
recently submitted license is for 470kt-LCE capacity (vs ~300kt by 2030E without the