REAL-TIME GLOBAL RESEARCH
2Q26 Solid Print; Groves‘ First Criticality Headlines Busy Quarter; Execution on All Fronts
Research evidence excerpt
J P M O R G A N
North America Equity Research
10 August 2026
Oklo Inc.
2Q26 Solid Print; Groves’ First Criticality Headlines
Busy Quarter; Execution on All Fronts
On Friday, Oklo reported 2Q26 results, where call commentary framed a continued
transition from strategy to execution across the business, headlined by Groves’ first
criticality on August 5. On the project backlog, OKLO advanced PJM
interconnection applications and transmission planning for the 1.2 GW AuroraOhio campus with Meta, while receiving DOE PDSA approval for Aurora-INL and
executing the Kiewit MOU to support fleet-level engineering, procurement, and
construction planning. On supply chain development, OKLO established
partnerships with several industry-leading enrichment and recycling services
providers, while catalyzing in-house development expertise via two acquisitions
this quarter (ARMEC, Creative Engineers). OKLO’s fuel strategy gained
significant call time, where management discussed an approach centered around
using DOE allocations initially, blending plutonium as a bridge fuel while thirdparty enrichment capabilities scale, and eventual fuel recycling. Separately,
broader nuclear policy modernization, including DOE's Genesis Mission and
Nuclear Lifecycle Innovation Campuses, offer potential tailwinds for
development and deployment. While commercial deployment still remains to be
proven, Groves’ criticality offers a positive data point, establishing a deployment
blueprint that de-risks execution across future powerhouse, fuel, and isotope
assets.
Groves reaches first criticality; structural construction completed in 229
days. OKLO achieved first criticality at its Groves Isotope Test Reactor on
August 5, 2026, completing greenfield facility construction in just 229 days.
The facility became the first DOE Reactor Pilot Program reactor to reach
criticality on private land rather than government land. Management
emphasized that Groves established a repeatable deployment blueprint, with
lessons learned around site development, procurement, construction, DOE
authorization, and startup that will inform future nuclear asset deployments
across the power and fuel platforms.
…