ReportGem ReportGem 中文

REAL-TIME GLOBAL RESEARCH

North American Utilities: 2Q26 Previews: OGE & POR

Published: 2026-07-14Institution: JPMorganPages: 14Original language: EnglishEvidence page: 1

Research evidence excerpt

North American Utilities: 2Q26 Previews: OGE & POR

J P M O R G A N North America Equity Research

14 July 2026

North American Utilities

2Q26 Previews: OGE & POR

Please find below our thoughts on OGE and POR into the quarter. North American Utilities

Aidan C Kelly AC

• OGE: large load tariff filing takes center stage, alongside focus on capex (1-212) 622-4912

catalyst path into next plan refresh After catching up with the company, we aidan.x.kelly@jpmchase.com

model 2Q26 adj EPS of $0.55, below the $0.57 Street median and up +2c YoY Jeremy Tonet, CFA

compared with $0.53 in 2Q25 on account of higher PISA contributions, (1-212) 622-4915

customer demand, and favorable weather, partially offset by higher O&M, jeremy.b.tonet@jpmorgan.com

interest expense, and share count dilution. With the large load tariff filing now Diana Niles

in hand, we view 2Q as a key stage for management to showcase how (1-212) 622-3328

incremental load can generate tangible customer benefits under the proposed diana.niles@jpmorgan.com

framework while preserving OK’s competitiveness for new investment. Key Eli Jossen, CFA

upcoming milestones include the September 9th hearing on Google’s special (1-212) 622-4113

contract and the November 3rd hearing on the proposed large load tariff. On the eli.jossen@jpmchase.com

J.P. Morgan Securities LLC

capex front, all signs point to a 4Q update on OGE’s 2025 SPP ITP opportunity,

which could support a capital plan refresh around 3Q/EEI if finalized.

Separately, the company’s all-source RFP stands as the other major rate base

growth catalyst, where staged filings could begin as early as 4Q as selections

crystallize across the 1.8GW resource need (potentially implying a mid-2027

timeline before capex is formally rolled into the plan). While the split between

The English excerpt is extracted automatically from the cited source page and may contain layout or recognition errors. It is never batch translated.

Open report viewer