Macquarie Equity Research Critical minerals preview
Near-term focus - FY27 volume growth
As all four lithium producers have a June year-end, we expect the market to shift its focus on
FY27 outlook in addition to the 4Q production result. Volume growth and capex intensity of
brownfield expansion could be a focus area given the recent lithium market volatility.
PLS
• Our base case has assumed capex of A$836m, A$1,136m and A$1,031m for FY27E, FY28E
and FY29E. These estimates are 25%/28%/26% above respective market consensus. We
attribute the difference to our conservative view on P2000 project cost escalation given
the PFS was conducted in mid-CY24. In addition, we have also assumed elevated deferred
stripping for FY27 as the company previously flagged that material moved in FY27 would be
~50% higher than FY26 levels.
IGO
• A fire incident occurred at Greenbushes' Chemical Grade Plant 3 (CGP3) facility on 9
June 2026. IGO subsequently confirmed that the fire has already been extinguished and
no injuries were reported. CGP3 has a nameplate capacity of ~500ktpa, but contributes
only marginally to FY26 output given ongoing ramp-up. IGO confirmed CGP1 and CGP2
remain operational. Full-year production guidance remains unchanged at 1,375-1,425kt of
spodumene concentrate.
• We expect the market to focus on IGO's FY27 production guidance which is expected at
its 4Q quarterly update. The guidance would also crystallise the fire damage and respire
time the CGP3. Our FY27E forecast production of 1.6mt (100%) of spodumene concentrate
at Greenbushes is 8% below market consensus of 1.74mt. We note media reports (link)
suggested that the repairs could take up to six months. An outage less than six months