实时全球研报
Behind the Meter Bonanza: Part 1 – What is the current landscape?
研报英文原文证据摘录
Behind the Meter Bonanza: Part 1 – What is the current landscape?
Accessible version
Integrateds, Refining, and Midstream
Behind the Meter Bonanza: Part 1 – What
is the current landscape?
Industry Overview
On-site gas opening sized at 80GW by 2030 23 July 2026 Corrected
Datacenter additions are rapidly moving the needle for US electricity demand, with the Equity
grid unable to keep up. Our analysis of a recent deep dive by our BofA colleagues United States
estimates an 80+ GW opening for onsite gas generation (unconstrained) by 2030. As Oil & Gas
power demand is outpacing the grid’s ability to connect in certain areas, several Jean Ann Salisbury
traditionally oil and gas companies, such as CVX, WMB, KGS and others have entered the Research Analyst
market for providing onsite behind the meter power to datacenters. This has been BofAS+1 646 855-1470
enabled by their access to turbines and engines, natural gas, and/or their project jeanann.salisbury@bofa.com
management capabilities. In a series of recurring notes, we will tackle the size of the gas Saurabh Pant
Research Analyst
BTM market and maintain a database of BTM announcements (available upon request). BofAS
+1 646 855 0199
A bottom up view -158GW announced BTM, 30-50% “real” saurabh.pant2@bofa.com
Michael Feniger
Using several sources (BNEF, Woodmac, Platts, company announcements), we piece Research Analyst
together 109 discrete announced projects representing 158GW of planned onsite gas BofAS
+1 646 855 1923
generation projects. This is the closest proxy to “Behind the Meter” Gas TAM that we michael.feniger@bofa.com
could find, though some are technically selling power into the grid as well as to a Andrew Obin
datacenter. Notably, most of these cases involve the datacenter developer also Research Analyst BofAS