Data Center Hubs “Ahead of Schedule” & 2GW of New Florida DCs
CITI'S TAKE
NEE continues to communicate data center hub progress to be “ahead of
schedule”, raised large load expectations at FPL from 6 to 8GW, and has Buy
tailwinds on renewables origination and recontracting (we think a potential
Price (24 Jul 26 16:00) US$89.78blue wave could help). We would not be surprised if the merger were to be
delayed at the VA commission by a few months and think the deal would Target price US$102.00↑
ultimately get through with some additional benefits to VA customers. from US$96.00
Stay Tuned on US/Japan DC Hubs — NEE previously targeted a Q2 definitive Expected share price return 13.6%
agreement with US/Japan on DC hubs in TX/PA, and today sent the message to the Expected dividend yield 2.9%
market that the project is “ahead of schedule” despite the lack of final agreement Expected total return 16.5%(parties involved and complexity of deal impact exact timing). We think the DC hubs
will go through regulatory processes outside the ERCOT Batch Zero/PJM RBP which Market Cap US$187,246M
accelerates timeline but is less trackable. We are positive on this opportunity.
Merger Timeline to Evolve, Affordability Matters in VA — We have been assuming
a ~6-month delay to the closing date, so a potential delay at the Virginia commission Price Performancebeyond the ~6-month statutory review timeline was not surprising to us. We spoke
with some VA regulatory experts and left thinking there would be some political (RIC: NEE.N, BB: NEE US)
noise, but ultimately, VA will allow deal to happen. In our view, key stakeholders in
本摘录由系统从所标注的 PDF 证据页直接提取并保留英文原文,不做批量翻译;登录后在阅读器切换中文时才按需翻译。