Kumba Iron Ore Ltd (KIOJ.J): 2Q26 prod/export in line vs CitiE; FY26 guidance maintained
研报英文原文证据摘录
Kumba Iron Ore Ltd (KIOJ.J): 2Q26 prod/export in line vs CitiE; FY26 guidance maintained
Flash |
23 Jul 2026 03:05:35 ET │ 10 pages
Kumba Iron Ore Ltd (KIOJ.J)
2Q26 prod/export in line vs CitiE; FY26 guidance maintained
CITI'S TAKE
Neutral Kumba reported -4% y/y decline in iron ore production to 8.8Mt (2Q25:
9.3Mt), in line vs the CitiE/guidance. The decline was driven by -16% lower Price (22 Jul 26 17:00) R252.34
production at Kolomela mine. Similar to production decline, exports also Target price R275.00
declined by -5% y/y to 9.2Mt (2Q25: 9.7Mt) and came in broadly line vs Expected share price return 9.0%
CitiE. The decline is largely driven by first of two planned 10-day railway Expected dividend yield 6.9%
logistics maintenance shutdown in May 2026. Total finished stock Expected total return 15.9%
declined to 7.0Mt vs 7.2Mt at 1Q26 end (7.5Mt at FY25 end) with majority
Market Cap R81,275M of stocks at the mines. Operational guidance remains unchanged, but
US$4,958M company now expects Sishen's unit cost towards the upper end of its
range and Kolomela towards the middle. The company also highlighted
that cost environment remains volatile on the ongoing developments in
the Middle East. Ephrem RaviAC
+44-20-7986-2462
2Q26 production lower y/y in line vs CitiE — Production at Sishen increased ephrem.ravi@citi.com
marginally by 1% y/y to 6.5Mt (2Q25: 6.4Mt); while production at Kolomela declined Shashi Shekhar, CFA
by -16% y/y to 2.4Mt (2Q25: 2.8Mt) due to plant maintenance in 2Q26, which
+91-22-4277-5028
coincided with the Transnet logistics maintenance shutdown.
shashi.shekhar@citi.com
FY26 guidance maintained — Iron ore production guidance maintained at 31- Krishan M Agarwal
33Mt; sales guidance at: 35-37Mt; Capex guidance at ZAR 13.2-14.2bn.