Global Electrical Infrastructure: Pulse check on the data center build out, power gen lead times and international competition
研报英文原文证据摘录
Global Electrical Infrastructure: Pulse check on the data center build out, power gen lead times and international competition
17 July 2026
U.S. Machinery
Global Electrical Infrastructure: Pulse check on the data center
build out, power gen lead times and international competition
Earlier this week, we met with the head of procurement at a leading data center developer, Chad Dillard
+1 917 344 8469 who also recently worked at a top 5 US electrical contractor. Below are the top 3 takeaways
chad.dillard@bernsteinsg.com from our conversation, which focused on the growing obstacles to data center construction,
the supply/demand environment in power generation (BTM + standby) and how China’s
Alasdair Leslie electrical equipment manufacturing footprint is expanding into the US under the radar.
+44 20 7762 4952
alasdair.leslie@bernsteinsg.com
It is harder to build a data center today than a year ago. More delays/cancellations in
Miguel Marques, CFA the first 4-5 months of this year than entirety 2025, driven by public aversion (power prices,
+1 917 344 8432 water usage, job losses). This uncertainty is forcing developers to hedge by multi-tracking
miguel.marques@bernsteinsg.com the same data center build in different geographic locations. The expert anticipates
60-65% of projects in pipeline to proceed as scheduled. As such, OEMs, particularly
Om Kela power gen (CAT, CMI, etc.), are stepping efforts up to protect backlog quality: higher +44 20 7550 2192
om.kela@bernsteinsg.com project viability standards (permits, financing & offtake), OEMs adding first right of refusal
to buy back equipment into contract if a project gets delayed. Although power remains
Specialist Sales a critical bottleneck, the skilled labor shortage is getting worse, especially amongst high