实时全球研报
The Power Behind AI – monthly data centre tracker: June edition
研报英文原文证据摘录
The Power Behind AI – monthly data centre tracker: June edition
Accessible version
Pan-European Utilities Themes
The Power Behind AI – monthly data centre
tracker: June edition
Industry Overview
Translating project announcements into power estimates 02 July 2026
Following our Data centre primer: the power behind AI from early December 2025, we Equity
launch the sixth edition of our monthly data centre (DC) demand tracker to monitor new Pan Europe
projects in Europe. Each month, we track the latest announcements and, where Utilities
appropriate, factor these into our capacity and data centre power demand forecasts for Peter Bisztyga >>
the most important European markets for our Utilities coverage, which account for Research Analyst
c90% of European data centre capacity today. Following Jun-26 announcements, we now MLI+44 (UK)20 7995 0535
see data centres raising overall electricity consumption by ~6.4%. peter.bisztyga@bofa.com
Noe Gonzalez >>
Sixth edition: bright month for announcements ResearchMLI (UK) Analyst
June delivered 26 projects, with total capacity unveiled near 5GW compared to ~1.1GW +44 20 7996 9022
noe.c.gonzalez@bofa.com
in May-26. This sharp increase in announced capacity is mainly attributed to the large
€45bn investment commitment made by SoftBank to build 3 data centres in France by JuliusResearchNickelsen,Analyst CFA >>
2031 (3.1GW of which 1GW already announced in January 2026), as part of the 2026 MLI (UK)
+44 20 7995 6027
Choose France summit held by Macron. As a result, June recorded the highest capacity of julius.nickelsen@bofa.com
any month in 2026. Of the ~5GW announced in June, ~0.9GW fall into our ‘High Marcin Wojtal >>
Confidence’ category. Within this category, we highlight an Ardian & Verne 200MW Research Analyst MLI (UK)
本摘录由系统从所标注的 PDF 证据页直接提取并保留英文原文,不做批量翻译;登录后在阅读器切换中文时才按需翻译。
打开研报阅读器