实时全球研报
Booming Datacenter pipeline and AI spending boom - the pivotal role of energy: POWERING UP EUROPE
研报英文原文证据摘录
Booming Datacenter pipeline and AI spending boom - the pivotal role of energy: POWERING UP EUROPE
Goldman Sachs Powering Up Europe
Executive summary
Booming Datacenter pipeline and AI spending boom - the pivotal role of energy
Europe’s datacenter pipeline – measured as the number of connection requests to
power grids across Europe – has surged to nearly 500 GW, equivalent to 1.5x current
European power demand, up sharply from our most recent projection of c.290 GW six
months ago and just 170 GW in January 2025. While some of this pipeline may be
speculative, we believe its rapid growth and its scale signal a major datacenter
construction phase ahead, spread fairly evenly across the continent. The EUDCA expects
+20 GW of additions by 2031, nearly tripling existing capacity, with around 60% already
under construction or FID. This would drive +1.5% power consumption growth pa from
2028-29, on our estimates. We continue to believe Europe will reach 65-80 GW of IT
capacity by 2035, with datacenters driving 1.5-2% power consumption pa later in the
decade, depending on AI Agents and AGI adoption. Meanwhile, Big Tech AI spending
keeps climbing, with the five main hyperscalers implying c.$700 bn of capex in 2026,
rising to nearly $1 trillion in 2027. Next year’s AI infrastructure spending would be
around ten times larger than in 2023, underscoring that the datacenter boom continues
in full force. We believe utilities will be pivotal to this process by providing energy,
scouting for land and grid connections, and reinforcing existing power grids to support
the incremental consumption.
Exhibit 1: The EU DC pipeline has more than doubled in one year
EU 28 GSe datacenter pipeline evolution, 2025-26 (GW)
c.480 GW
2025 EU-28 Consumption: c.320 GW
c.290 GW
c.280 GW
c.230 GW
c.170 GW