普通外文研报
Moreld-Firms up Vår contract; derisking 2027 estimates-06/26/2026
研报英文原文证据摘录
Moreld-Firms up Vår contract; derisking 2027 estimates-06/26/2026
Moreld
NEWSFLASH | 26 JUN 2026
Firms up Vår contract; derisking 2027 estimates
Moreld subsidiary Ocean Installer has been awarded a major SURF contract by Vår Energi on the Balder Next project. The
award was expected, but the contract value was larger than assumed. The contract significantly derisks 2027 estimates,
with risk increasingly skewed to the upside. With the company trading at >20% FCF yield, expectations are arguably low
and improved visibility positive. BUY, TP NOK 26
Firms up major contract with Vår Energi
• Moreld subsidiary Ocean Installer has been awarded the SURF installation contract for the Balder Next New Wells project on the NCS,
sanctioned by Vår Energi earlier this month. This adds to its previously awarded pipeline EPC contract for the Balder Next project (awarded
in Q4’25)
• The total contract value is expected to be NOK ~2.5bn, with further options (NOK ~0.5bn). This is above our initial expectation. The project
is fast tracked, with the majority of the subsea work in 2027 (~75% of firm value)
2027 shaping up well for Ocean Installer; estimate risk on the upside
• Including this award, Ocean Installer has ~70-75% revenue coverage in 2027e, utilizing ~50% of budgeted vessel days (on a 300-day
basis). As previously noted, we believe the company is also well positioned for a (large) SURF contract at Equinor at Troll 3 stage 3 (TWIN)
project, with execution likely 2027-28 (Ocean Installer currently working on stage 2)
• In sum, 2027 thus is shaping up to be a strong year, with Ocean Installer also having secured smaller contracts and some Q1 utilization
(unlike 2026). We see estimate risk skewed to the upside, currently discounting NOK ~700m in EBITDA (vs NOK 835m in “strong” 2025
本摘录由系统从所标注的 PDF 证据页直接提取并保留英文原文,不做批量翻译;登录后在阅读器切换中文时才按需翻译。