Sentia
NEWSFLASH | 16 JUN 2026
Adding to the data centre order book
SNTIA has announced a contract with Skygard to build Phase 2 of the OSL1 data centre at Økern, covering 12,000 m², roughly
half of the 25,000 m², 20 MW (Tier III-certified) facility. Assuming Phase 1 carried a similar value, the implied NOK ~30m per
MW sits comfortably alongside the 25 MW centre SNTIA is building for Aker Nscale in Narvik (NOK ~28m per MW). On its
own the order accounts for only 12% of our Q2'26e order intake, but we see the read-through as more important than the
headline figure. SNTIA continues to build its position in the rapidly growing Nordic data centre segment, where each award
strengthens its candidacy for subsequent contracts (a segment that sets a high bar on pace and quality). These projects
should also be margin-accretive, helped by the pace of delivery, which we understand to run closer to 6-8% versus 4-6%
across the broader portfolio. Buy, TP NOK 95.
Marcus Gavelli
+47 24 02 81 12, marcus.gavelli@paretosec.com
Torbjørn Nerheim
+47 24 02 81 18, torbjorn.nerheim@paretosec.com
For disclosures on relevant definitions, methods, risks, potential conflicts of interests etc. and disclaimers please see www.paretosec.com. Investment Recommendations should be reviewed in
conjunction with the information therein. When distributed in the US: This document is intended for institutional investors and is not subject to all of the independence and disclosure standards
applicable to equity/debt research reports prepared for retail investors. This material is considered by Pareto Securities to qualify as an acceptable minor non-monetary benefit according to Directive
本摘录由系统从所标注的 PDF 证据页直接提取并保留英文原文,不做批量翻译;登录后在阅读器切换中文时才按需翻译。
打开研报阅读器