1Q26 Review; Construction Progressing, Regulatory Momentum Building. Reit OW, $122 PT.
研报英文原文证据摘录
1Q26 Review; Construction Progressing, Regulatory Momentum Building. Reit OW, $122 PT.
May 12, 2026
broader regulatory shift in favor of non-LWR technologies. Taken together,
we believe these frameworks make Oklo's early assets strategically more
valuable, as they speed the transition into NRC commercial licensing.
Site development and procurement update. For the Aurora-INL, long-lead
procurement work is advancing across major systems, and site preparation
and construction activities are progressing in the field:
●A3F Fuel Facility - early construction activities are complete and final
design deliverables are complete, with the construction contract award
expected as the next major execution milestone.
●Groves Test Reactor - the company completed construction in 229 days
and received the Certificate of Substantial Completion, with the next
execution focus on final installation of reactor equipment and fuel
delivery, as the company remains on pace for July 4, 2026 criticality.
Commercial development continues to expand. Oklo's plans with Meta
(OW, covered by D. Mathivanan) to develop a 1.2 GW advanced nuclear
power campus in Ohio progressed in the quarter, with the submission
of their interconnection applications on April 27, 2026. Moreover, the
company received a Notice of Intent to Award from the Defense Logistics
Agency for an Aurora-derived powerhouse at Eielson Air Force Base in
Alaska. Site characterization is underway, and ground investigations are
expected to begin in Summer 2026.
On the Fuel side, the company's Advanced Fuel Center in Tennessee is
going through site preparation, while the NRC application readiness review
is continuing. Within Isotopes (now known as Oklo Isotopes), the Idaho
Radiochemistry Laboratory received an NRC Material Handling Permit, and