KGHM Polska Miedz SA (KGH.WA) 2Q26 Results Management Meeting Highlights
Research evidence excerpt
Flash |
20 Aug 2026 08:40:03 ET │ 10 pages
KGHM Polska Miedz SA (KGH.WA)
2Q26 Results Management Meeting Highlights
CITI'S TAKE
Below please find the key issues that were raised during KGHM’s 2Q26
results conference.
Sierra Gorda - The project has final approval on the $725m investment for a fourth
production line, which is expected to boost the mine's metal production by 20% and
further lower costs upon its completion in 2H2030 (with the biggest outlays in 2027
and 2028, and employment increases in 2028). The project would be funded by debt
and operating cash flow.
Robinson - The mine continues to face significant operational headwinds from
difficult ore and equipment failures, which will temper group performance in the
near-term (the lower-quality ore phase is expected to last until a shift to a better
part of the deposit in 2028)
Dividend - The company remained non-committal on a specific dividend for 2026,
prioritizing investment and balance sheet strength.
Sell
Price (20 Aug 26 12:49)
Zl335.25
Target price
Zl209.00
Expected share price return
-37.7%
Expected dividend yield
0.7%
Expected total return
-36.9%
Market Cap
Zl67,050M
US$18,139M
Rafal Wiatr, CFAAC
Cost Optimization - KGHM is targeting ZL 1bn in savings by 2028, compared to
2024. According to management, the program has already achieved ZL 300m in
savings after its first year.
Inventory & Cash Flow - 2Q26 cash flow was negatively impacted by a planned
build-up of anode inventories (peaking at a value of ZL 2.5bn) ahead of the Głogów II
shutdown. Management gave firm assurance that this inventory is now being
processed and the cash will be released in 3Q-4Q26.
Wage costs - In 2Q26 wage cost (at parent company level) was driven by a bonus
paid to workers and a contribution to the price and reward fund (over ZL 300m)
required by the collective agreement. The company does not plan to continue this
contribution over the reminder of the year.
Potential M&A - The company is looking at South America, North America, and
North Africa (specifically Morocco), preferring stable jurisdictions. They are cautious
as copper projects are currently "overstated in price." One priority is exploring
…