Northern Star Resources Ltd.: KCGM site visit takeaways
研报英文原文证据摘录
Northern Star Resources Ltd.: KCGM site visit takeaways
underwrite branko.skocic@jpmorgan.com
yet is the 12 months between here and steady state, and that is where the earnings J.P. Morgan Securities Australia Limited
risk sits. We retain Neutral. Zane Guo
(61-3) 9633-4020
• Built to remove operating cost; not minimise upfront capex. The plant is zane.guo@jpmorgan.com
exceptionally well built and deliberately designed for a multi-decade life. The J.P. Morgan Securities Australia Limited
capital is sunk; what matters now is how much future cost the design removes.
NST has gone from five mills to three larger units, replaced +30 pumps,
installed permanent cranes and monorails in place of mobile cranes and
contractor crews, and designed in rotatable crusher components, direct
maintenance access, dedicated belt-change facilities and dual-sided mill
relining. Management’s intent is to halve processing cost/t against FY26
(JPMe ~A$45/t) on a real basis at steady state from FY29. The denominator
matters, since FY26 was struck on a plant running at 79% of nameplate, and
we would frame the prize as costs better defended against inflation rather than
absolutely halved. But it is a larger opportunity than we had credited, and the
visit increased our confidence that it is technically credible.
• Power is material, but back-ended. NST targets roughly one-third lower
power costs through the Parkeston JV (110MW, 50%-owned), new thermal
generation and a renewables package with battery storage. Components
commission progressively, with the full system expected in place by late CY28.
Power sits inside the processing cost/t target, which makes the complete cost
reset an FY29 proposition rather than an FY27-28 earnings driver. Kalgoorlie's