J P M O R G A N North America Equity Research
29 July 2026
Independent Power Producers:
Sparks & Quarks
2Q26 IPP Previews; IPP Fundamentals Remain Intact
Despite Broader Market Vol; News Flow; IPPs Lag
• Sentiment Check: IPP lags alongside momo and volatility sell-off. IPPs Head of North America Power,
lagged on the week as the AI complex continues to underperform the broader Utilities, Midstream, LNG, and
market. While fundamentals remain attractive for the group, we would not be Nuclear
surprised to see continued weakness in the price action as industrial names and Jeremy Tonet, CFA AC
hyperscalers report earnings. On the regulatory front, while market uncertainty (1-212) 622-4915
has hampered the pace of contracting, investor conversations have touched on jeremy.b.tonet@jpmorgan.com
whether IPPs would have interest in controlling their destiny similar to wires Vrathan Reddy
names that have discussed leaving PJM. (1-212) 622-4692
vrathan.reddy@jpmchase.com
• PJM proposes IRAS to enhance grid reliability. In the evolving connect and Aidan C Kelly
manage issue, PJM recently proposed Interim Resource Adequacy Service (1-212) 622-4912
(IRAS) whereby large loads, defined as end‑use load ≥50 MW at a single site aidan.x.kelly@jpmchase.com
(including post–June 1, 2027, incremental ramps that push a site over the Diana Niles
threshold), can interconnect without immediate new capacity. However, this (1-212) 622-3328
would require load reduction (or backup supply where permitted) under diana.niles@jpmorgan.com
limited, reliability-driven conditions. PJM would run a centralized Large Load Eli Jossen, CFA