Tracking Local Opposition to U.S. Data Centers w/ Data Center Watch | REPLAY
研报英文原文证据摘录
Tracking Local Opposition to U.S. Data Centers w/ Data Center Watch | REPLAY
Global | Washington Strategy June 18, 2026
Opposition typically emerges before or duringTracking Local Opposition to U.S. Data Centers
zoning and permitting decisions
The Lifecycle of Data Center Oppositionw/ Data Center Watch | REPLAY
Continuing our work on politics around AI and data centers (here,here & here),
we hosted Miquel Vila, Lead Researcher at Data Center Watch. KTs:1) 75+ data
center projects worth $130bn were blocked or delayed in Q1 2026; 2) Opposition
.
has expanded beyond local disputes to anti-AI sentiment; 3) Permitting process Source:Center WatchJefferies Presentation by Miquel Vila, 10aLabs/Data
is the key catalyst; 4) Opposition doubled w/ 600k+ petition signatures; 5)
Bipartisan politics is turning data center opposition into a policy risk.
1) Data center opposition is accelerating and becoming a structural constraint on AI
infrastructure (see here & here). At least 75 data center projects worth $130bn were blocked
($53bn) or delayed ($76bn) in Q1 2026, matching the scale of all of 2025 in just three months. Aniket Shah, PhD * | Head of Sust. &
Opposition is now present in 49 states and is no longer confined to local "not-in-my-backyard" Transition Strategy
concerns, reflecting a structural shift in how projects face resistance across the U.S. +1 (212) 323-3976 | ashah14@jefferies.com
Yujin Kim * | Sust. & Transition Strategy
2) Opposition has expanded to broader anti-AI sentiment. While early resistance was driven by Associate
community-level concerns around large industrial projects, a growing share now reflects national +1 (212) 778-8314 | ykim4@jefferies.com
narratives about AI risks, with data centers viewed as the physical embodiment of AI.