PowerPoints: AVA DC Pause, PWR Breaker JV, AEE/AMZN, WMB Constitution
研报英文原文证据摘录
PowerPoints: AVA DC Pause, PWR Breaker JV, AEE/AMZN, WMB Constitution
USA | Power & Utilities EquityJuneResearch16, 2026
Exhibit 1 - Coverage Universe Equities MostPowerPoints: AVA DC Pause, PWR Breaker JV,
AEE/AMZN, WMB Constitution Correlated to the AI Theme
AVA data center MOU on pause while Spokane City Council 1-yr data center
moratorium vote pending. PWR and HICO JV for H-V breaker manufacturing
in the U.S. AEE-AMZN Missouri data center: positive development but in
AEE's plan. Constitution back in the news after President Trump 'accuses' NY
Governor Hochul of backing out of alleged offshore wind for pipeline deal.
.
Source: FactSet, FTSE Russell, & Jefferies LLC
AVA: Data Center MOU on Pause, Spokane City Council To Vote On 1-Yr Moratorium. Avista
(AVA) announced it is pausing data center development outlined in a prior MOU. This follows local
community pushback and a Spokane City Council ordinance for a 1-yr data center moratorium;
vote within a week. Timing of ramp and ultimate development is at risk given the ordinance as is the ~
$350Mn upside capex to serve the customer. Challenging setback so soon after original 8K.
PWR: New HICO JV reinforces broader scope capture in HV transmission. HICO announced a
JV with Quanta (PWR) to localize HV breaker manufacturing in the U.S. The new Hyosung HICO
Breaker JV will operate from Quanta’s Canonsburg facility; operations targeted to begin July 1,
2026. Supports the thesis that 765kV transmission build-out is not just a labor opportunity, but a broader
equipment, manufacturing, and turnkey delivery opportunity where PWR can capture more of the value
chain.
AEE: AMZN Announces Montgomery County Data Center. Amazon (AMZN) announced a data
center project in Montgomery County, Missouri to be served by Ameren Missouri (AEE).