Energy Infrastructure: FERC Orders Prioritize Data Center Speed-To-Power
研报英文原文证据摘录
Energy Infrastructure: FERC Orders Prioritize Data Center Speed-To-Power
Global Research SECTOR NOTE
June 18, 2026
■WRG Energy Transition & Sustainability Energy Infrastructure: FERC Orders Prioritize
Data Center Speed-To-Power
TD SECURITIES (USA) LLC - WASHINGTON THE TD COWEN INSIGHT
RESEARCH GROUP - USA
FERC orders direct ISO/RTOs to accelerate data center studies and offer new more flexibleMACRO POLICY
interconnection pathways. FERC seeking to mitigate 'affordability' risk through 'cost recovery
John Miller agreements.' We see action as positive for data center developers and IPPs and neutral for
202 868 5306
T&D utilities due to GET requirements.
john.p.miller@tdsecurities.com
Sector Impacts: Utilities; Data Centers; Industrials (E&Cs, Electrical Equipment)
Cooper Pryde
212 468 7804
cooper.pryde@tdsecurities.com What Happened?
Today, FERC issued a series of orders (HERE) requiring ISO/RTOs to accelerate large load (dataTD SECURITIES (USA) LLC
center) grid interconnection timelines, while looking to mitigate retail costs shifts through new
EQUITY RESEARCH
'cost recovery agreements.
Shelby Tucker, CFA
646 562 1322 Policy Takeaways (John Miller, TD Cowen WRG)
shelby.tucker@tdsecurities.com
We view today's FERC action as positive for data center developers and as confirming co-
Eli Mingos location as the go-to model for large loads in ISO/RTO markets.
646 562 1407
eli.mingos@tdsecurities.com We see FERC's reforms as accelerating data center study timelines and offering new flexible
(less expansive) transmission interconnection pathways - both actions benefit the speed-to-
power push. In pivoting from the slower rulemaking process to a series of ISO/RTO-specific
'show cause' orders, FERC has accelerated the timeline in which reforms can be deployed.