BE: Crusoe Wyoming Data Center Paused
研报英文原文证据摘录
BE: Crusoe Wyoming Data Center Paused
EQUITY RESEARCH QUICK TAKE
RBC Capital Markets, LLC
Christopher Dendrinos, CFA (Analyst)
Laura Deng (Senior Associate)
June 9, 2026
Bloom Energy Corporation
Crusoe Wyoming Data Center Paused
NYSE: BE | USD 259.61 | Outperform | Price Target USD 335.00
Sentiment: Neutral
Our view. It's unclear at this time why Project Jade (Crusoe WY) is being paused, though Crusoe has indicated it came at the
request of its customer. BE is providing 900 MW of fuel cells for the project, but we do not believe this will impact its outlook.
The site also proposes using 2 664 MW MHI M501JAC CCGTs, 3 51 MW GEV LM6000 aeroderivatives, 13 34.5 MW GEV LM2500
aeroderivatives, 1 Pro Energy (PE) 6000, and 24 temporary 34.5 MW GEV LM2500 aeroderivatives.
In the same area, Microsoft has been actively purchasing land to expand its existing datacenter footprint and on June 8, the
company met with City Council members to propose the annexation of 3.5k acres of land to expand its campus. However, this was
met with some community push back, and the proposal is still pending approval.
Public opposition against datacenters in WY has been building and in prior weeks Cheyenne City Council rejected a proposed
12-month moratorium on new datacenters and at the same time the state governor signed an EO establishing a WY datacenter
development framework “Data Centers the Wyoming Way,” focused on attracting investment while protecting ratepayers, natural
resources (water), local communities (sustainability), and transparency.
Development delays due to community push back has been growing and BE customers have not been immune to these challenges.
However, this has also created opportunity for the company. BE's solution offers lower noise levels, no water usage, and a cleaner