Workin' The Lats: Oracle's RPO and Ramp Support Positive BE Power Readthrough
研报英文原文证据摘录
Workin' The Lats: Oracle's RPO and Ramp Support Positive BE Power Readthrough
Energy | Power & Utilities
June 11, 2026
Nicholas Amicucci, CFA Workin' The Lats: Oracle's RPO and Ramp
212-812-2931
nicholas.amicucci@evercoreisi.com Support Positive BE Power Readthrough
Sharon Wang Yesterday post-close Oracle (covered by Kirk Materne) reported record
212-653-8999 4Q/FY26 results. Per Oracle's 4Q/FY26 earnings release, remaining
Sharon.Wang@evercoreisi.com performance obligations (RPO) reached $638B, up 363% y/y and
+$85B sequentially, and cloud infrastructure (IaaS) revenue rose 93%
to $5.8B. We view the print as a positive readthrough for Bloom
Energy (BE, Outperform, $295 PT), as we believe it supports the
scale, duration, and pace of the AI power demand underlying our
thesis. The most direct readthrough came during the call as ORCL
management outlined its five largest sites including its Doña Ana
County, New Mexico campus (Project Jupiter) that management
described as having a "power design based on gigawatts of clean,
energy-efficient Bloom fuel cells." We view the pace of ORCL’s
build-out as the most meaningful readthrough for Bloom’s orderbook
and near-term performance. During FY26 ORCL reported delivering
>1.2GW to customers and management guided F1Q27 deliveries to
approach 1GW. Management indicated the delivery ramp is backed by
$67B of AI infrastructure contracts signed in the quarter and a planned
FY27 net cash CapEx outlay of roughly $70B (before $20-25B of
customer prepayments). Against this backdrop, we would note that
under the expanded master services agreement disclosed in Bloom
Energy's April 13, 2026 press release, Oracle intends to procure up to
2.8 GW of Bloom fuel cell capacity, with an initial 1.2 GW contracted
and deploying into next year.