Brazilian Utilities: June 2026 - Looking back and what‘s next
Research evidence excerpt
Brazilian Utilities: June 2026 - Looking back and what‘s next
Global Research
2 July 2026ab
Brazilian Utilities Equities
AmericasJune 2026 - Looking back and what's next
Utilities
Giuliano Ajeje
June 2026 - Capacity de-risked, flexibility repriced Analyst
June changed the conversation in Brazilian utilities. The sector is no longer giuliano.ajeje@ubs.com
debating whether Brazil needs capacity, flexibility and grid investment. It does. The +55-11-2767 6371
investable question is now who gets paid, who funds the bill, and which balance Henrique Simoes
sheets can move before regulation catches up. The LRCAP overhang largely cleared Associate Analyst
in favor of continuity. The TCU preserved the auction results despite keeping the henrique.simoes@ubs.com
alleged overpricing review alive, reversing the suspension risk that had dominated +55-11-2767 6308
May (link). That matters. Thermal beneficiaries are de-risked near term - Eneva Julia Ongarato
stands out on headline exposure - while the incremental capacity charge of roughly Associate Analyst
R$2.3bn from Apr-26 to Apr-27 moves into consumer tariffs. The disqualification of julia.ongarato@ubs.com
nine EPP thermal projects, totaling around 1.7 GW, also tightened the message: +55-11-2767 6694
contracted capacity may survive scrutiny, but not every marginal project will (link).
J&F’s failed late qualification reinforces the same point. The state wants reliability,
but within a gatekeeping framework that is becoming more selective.
Storage was the bigger structural shift. Aneel’s BESS framework removed double
grid tariffing for assets under full ONS dispatch, while the MME split the first storage
LRCAP into two December auctions - one with local-content requirements, one open